At the Pulaski County drainage meeting, Jake reported the project team had completed a site visit and a review of 90% design plans for the Grama tile project and identified a few outstanding items.
"As Jenny said, we met last week to go over the 90% design plans," Jake said, describing a site visit and a plan 'page turn.' He told the group the team wanted additional televising of one existing line to inform final design decisions.
The update was presented as informational; the transcript records no formal vote or directive tied to the 90% plans. Jake and meeting participants identified outstanding items that staff will need to address before final design approval, but the record does not include a schedule for resolving those items or a next meeting date for a decision.
The presentation suggests the project is near final design, with additional field verification needed. The transcript does not state funding sources, construction timing or an approval date.