The Village of Hortonville Board of Trustees approved a second pay application to Northeast Asphalt totaling $143,100.81 for completed work on the Fountain Court and John Street projects.
Village staff told trustees the projects are complete and that the final cost came in under the engineer’s earlier estimate because less material was required. “We’re actually, under what the estimated budget was,” a staff member said during the meeting.
Trustees moved and seconded a motion to approve the payment; the board conducted a roll call and the motion carried unanimously. The board held a small retainage while confirming landscaping and material growth.
Background: The payment covers contracted paving work; trustees said they are holding a limited amount of funds back pending final turf establishment and related small items. The contractor named on the pay application was Northeast Asphalt.
Speakers and evidence cited for this item appeared under the agenda label “Discussion and possible action on John Street, Fountain Court, project k, application number 2.”