Engineering Department Approves Change Orders for Downstone Street Streetscape Project

July 25, 2025 | Valparaiso City, Porter County, Indiana


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Engineering Department Approves Change Orders for Downstone Street Streetscape Project
Change orders for the downtown streetscape project in Valparaiso received unanimous approval during the City Board of Works meeting on July 25, 2025. The Engineering Department presented three significant change orders aimed at addressing unforeseen costs and enhancing the project.

Change order 2, amounting to $41,267, covers additional mobilization charges due to work extending into 2025. Change order 3, totaling $49,152, addresses costs related to underground construction work and delays. Lastly, change order 4 involves a material cost adjustment for larger planters, aligning with previous installations by the Parks Department.

Funding for change orders 2 and 4 will come from the Redevelopment Commission (RDC), which has already approved these expenses. Change order 3 will be financed through the sanitary sewer and stormwater budget, with prior approval from the utility board.

The total increase to the contract stands at $613.45, reflecting the necessary adjustments to keep the downtown project on track. The board's swift approval underscores the commitment to enhancing Valparaiso's urban landscape while managing budgetary challenges effectively.

View full meeting

This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

View full meeting

Comments

    Sponsors

    Proudly supported by sponsors who keep Indiana articles free in 2025

    Scribe from Workplace AI
    Scribe from Workplace AI